4 The profitability and technical data studies are provided in report format to owners and funders for acceptance. This type of report, used to solicit funding, is referred to as a(n) _____.

A. Project feasibility study.

B. Economic evaluation analysis.

C. Risk management manual.

D. Prospectus.

E. None of the above

正确答案:D


甘特图和网络图的区别是什么?( )

A.历时

B.任务

C.节点

D.时差

正确答案:C


142 The Utility Theory _____ .

A. considers risk propensity of the decision maker.

B. attempts to formalize management's risk considerations.

C. works well with decision tree analysis.

D. is considered highly theoretical.

E. All of the above

正确答案:B


7 Communication always makes use of.

A. symbols

B words

C. language

D. gestures

E. All of the above

正确答案:E


● The most frequently used construct in Precedent Diagramming Method is:

A Start to Start.

B Finish to Finish.

C Start to Finish.

D Finish to Start.

E Dummy activity.

正确答案:D


The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A . buyer's risk

B . consumer's risk

C . producer's risk

D . type I error

E . B and D only

正确答案:B


2021项目管理师考试真题精选及答案5篇 第2篇


你正在领导一个项目团队开发一种非常复杂的产品,这种产品可以通过电离子直接作用于人的大脑前额皮层来刺激人的神经系统。由于项目在技术上非常复杂,使得你必须对成本进行严格地跟踪和控制,其中主要包括直接成本和间接成本(企业一般管理费用)。你发现对间接成本的管理特别困难,这是因为它:( )

A.是按照“一个项目一个项目”的方式来处理的

B.只代表直接的劳动成本

C.只代表项目需要的设备和原料

D.项目经理不能控制这部分成本支出

正确答案:D


进度报告的50-50规则被用于—— ( )

A.计算精确的EV

B.提供一个EV的良好估计值

C.确定进度偏差

D.确定货币的进度偏差

正确答案:B


133 Using the WBS shown in the Special window, a typical work package would be:

A. Software development

B. Systems design

C. Coding

D. A, B, and C

E. None of the above

正确答案:E


4个质量事件是:

a. 定义,系统,执行标准和测量.

b. 规格,目标,顺序一致和定义.

c. 质量成本,零缺陷,测量和系统.

d. 规格,持续检验,7个作用和质量成本

正确答案:B
b. [参见学习手册.  质量概念. 爱尔兰  I-6 页。]


110 The Cost Performance Index (CPI) measures

A. total costs

B. performance over a period of time

C. costs at a point of time

D. variable costs

E. All of the above

正确答案:C


188 All of the following are categories of a milestone in a schedule except:

A. End date.

B. Contract dates.

C. Key events scheduled.

D. Imposed dates.

E. Task duration

正确答案:E


2021项目管理师考试真题精选及答案5篇 第3篇


管理储备被用于——( )

A.项目开始时确定的风险

B.项目开始时没有

C.在其发生前不能知道的风险,因为它们是外部风险

D.在其发生前不能知道的任意风险

正确答案:D


以下哪个工具可以用于分析设计、确定其功能、以及评估如何在成本合算的情况下提供这些功能

A、 帕累托图

B、 Kanban

C、 配置管理

D、 价值分析

正确答案:D


在属性抽样中:

A、 结果可能吻合,也可能不吻合

B、 可以采用评估吻合度的连续等级给出结果打分

C、 强调常态过程偏差

D、 着重于确定结果是否处理特定的控制极限内

正确答案:A


你负责管理一个数据中心 建设 项目,涉及到10个主要干系人,他们分别代表7个大公司。这个大项目涉及到物业、装修、强电、弱电、计算机硬件、系统软件、系统集成和 IT 咨询等8个不同的承包商,他们的工作必须相互协调。你直接管理的项目团队有六个团队领导。每个团队领导各带领一支由7人组成的团队。因此,你认识到必须投入大量的精力进行有效的整体变更控制。这意味着你主要关心:( )

A.促使引发变更的因素朝有利的方向发展;确定变更已经发生;管理实际发生的变更

B.保持基准线的整体性,整合产品和项目的范围,在各个不同的知识领域之间协调变更。

C.整合来自项目的不同职能部门的可交付成果

D.建立一个变更委员会来监视所有的项目变更。

正确答案:A
总体变更控制关心的是促使引发变更的因素朝有利的方向发展;确定变更已经发生;管理实际发生的变更。总体变更控制要求保持基准线的整体性,整合产品和项目的范围,在各个不同的知识领域之间协调变更。包括协调和管理项目进程中的变更,包括的行为有范围变更控制,范围验证,进度变更控制,成本变更控制,质量控制,风险监视和控制,以及合同 管理。而变更委员会是属于变更控制系统的一部分。


你正在管理一个大型的国际博采项目。你的客户最近赢得了马尔科姆·伯德瑞奇奖,因此他特别强调项目质量。合同上要求你要准备一份项目计划和一份质量管理计划。你的核心团队正在准备质量管理计划。在这个计划编制中你们第一步要做的是

A.确定在质量管理过程中使用的具体测量方法

B.明确项目的质量标准

C.制定项目的质量政策

D.明确项目质量管理的具体角色和责任

正确答案:C


All the techniques described below can be used to keep a meeting focused except:

A Recall agenda items/purpose of meeting

B Summarize discussion periodically

C Encourage pursuit of interesting new ideas

D Rephrase unclear ideas presented by group members

E All are acceptable techniques

正确答案:C


2021项目管理师考试真题精选及答案5篇 第4篇


在谈判中最常见的问题是—— ( )

A.每一方都误解另一方说的话

B.每一方都对另一方失望

C.一方试图扰乱另一方

D.一方只想着下一步怎么说,而没有去听对方所说的

正确答案:A


在项目收尾阶段很多项目经理都倾向于尽可能推迟人员的重新分配这是因为( )

A.他们被迫面对这一过程中可能发生的人际冲突

B.他们相信没有人想离开项目

C.职能经理不愿意让 项目成员回到职能部门

D.项目队伍成员不愿意转到一个新分配的岗位上

正确答案:A


下列描述的所有技术都是使会议不走题除了( )

A.重申会议议题及目的

B.分阶段对会议作一总结

C.鼓励由新的有趣的主意

D.对成员提出的不清晰意见作一解释

正确答案:C


120 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments

正确答案:A


148 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

正确答案:E


以下哪一条最贴切的描述了成本控制?

a. 是对未来项目进行过程中发生的可能性,不确定性及夸大性进行趋势估定的方法.

b. 是组合并预计项目超出其生命周期的费用的方法

c. 是制定预算,标准及监测系统以衡量并管理项目投资成本的方法

d. 是在不断进行的基础上搜集,积累,分析,检测,报告并管理成本的一种方法.

正确答案:D
   d [PMBOKTM,成本管理 7.4章节的成本控制。也可见学习手册,成本控制 章节。前3
个答案涉及成本的确立、组合和发展。而答案D是在成本估算和成本预算完成后收集
数据。]


2021项目管理师考试真题精选及答案5篇 第5篇


The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.

正确答案:A
A


83 A computer tape which contains historical project information is called ____ tape.

A. Database

B. Baseline.

C. Archive.

D. Lessons learned.

E. Life cycle summary

正确答案:C


2 From an operating or functional perspective, there are various objectives of purchasing and materials management. Which is not one of these objectives?

A. To buy competitively

B To support company operations with an uninterrupted flow of materials and services

C. To develop reliable and effective sources of supply

D. To achieve maximum integration with the other departments of the firm

E. To attain approval from each department of every purchase

正确答案:E


以下哪一个因素对团队沟通贡献最大?( )

A.外部反馈

B.绩效评价

C.项目经理解决团队的冲突

D.同地集结

正确答案:D


66 Which of the following activities can be considered as part of risk mitigation

A. risk identification

B. purchasing insurance

C. assessment of outcomes

D. assessment of probabilities

E. C and D only

正确答案:B


Risk management requires an understanding that _____ .

A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

B risk identification must be directly aligned with the Work Breakdown Structure.

C it is merely advanced preparation for possible adverse future events.

D it does not imply complete control of events

E All of the above.

正确答案:E