21年项目管理师经典例题8卷 第1卷


撰写项目进展报告是所使用的“50-50”规则主要用于

A.计算精确的增殖

B.比较准确的估计挣值的大小

C.判断进度方差

D.以货币值来判断进度方差

正确答案:B


The Project Manager has the responsibility of knowing what kind of message to send because his _____ may avoid communications barriers.

A business interfaces

B output

C technical experience

D priorities

E training methods

正确答案:B


116 Which of the following are part of the purchasing cycle:

A. define need

B. prepare and issue purchase order

C. inspect incoming goods

D. All of the above.

E. A and B only

正确答案:E


The WBS is:

A.An organization oriented family tree of the project.

B.A task oriented family tree of the project.

C.A cost centered structure of the project.

D.Only required on large complex projects where separately identifiable work packages are difficult to construct.

E.None of the above.

正确答案:B
B


项目计划对于变更控制非常重要,这是因为它可以:

A、 针对管理哪些变更提供基准计划

B、 为执行项目提供信息

C、 提醒项目团队哪些问题将来可能引起问题

D、 在整个项目期间变化

正确答案:A


Cost Plus Percentage of Cost contracts are more desirable for the:

A owner

B buyer

C seller

D contractor

E C or D

正确答案:E


58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.

A. Trend line.

B. Trend analysis.

C. S curve.

D. Percent completion report.

E. Earned value report

正确答案:C


21年项目管理师经典例题8卷 第2卷


由谁最终负责确定和管理项目风险 ( )

A.项目发起人

B.经理

C.团队

D.经理和项目发起人

正确答案:A


团队发展以下列哪项为基础( )

A.项目的组织结构

B.为项目团队提供的培训

C.每个团队提供的培训

D.项目中相互合作、充分沟通和相互信赖的组织氛围

正确答案:C


10 Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:

A. Capital budgeting process.

B. Overhead rates.

C. Contracts and administration costing system.

D. Fringe benefits packages.

E. None of the above

正确答案:B


6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

B Development of design phase

C. Execution phase.

D. Termination phase.

E. None of the above

正确答案:C


如果因为缺少员工培训和恰当的生产控制而生产控制而必须返工,那么多少返工成本可以直接归因于生产线上的工人?( )

A.大约15%

B.大约50%

C.没有

D.100%

正确答案:A


The basic terminology for networks includes:

A.Activities, events, manpower, skill levels and slack.

B.Activities, documentation, events, manpower and skill levels.

C.Slack, activities, events, and time estimates.

D.Time estimates, slack, sponsorship involvement, and activities.

E.Time estimates, slack time, report writing, life cycle phases, and crashing times.

正确答案:C
C


如果项目经理不关心个人目标而是关注关系问题,那么他采用的是哪类冲突解决方法?( )

A.得-失

B.屈服-失

C.失-离开

D.妥协

正确答案:B


21年项目管理师经典例题8卷 第3卷


The most common form. of organizational communication is

A Upward to management

B Downward to subordinates

C Horizontal to peers

D Horizontal to customers

E All of the above

正确答案:E


由谁最终负责确定和管理项目风险

A、 项目发起人

B、 经理

C、 团队

D、 经理和项目发起人

正确答案:A


用于工作中心的单一任务时的在WBS中的检查点通常是指 ( )

A.工作包

B.子工作任务

C.工作任务

D.帐户编号

正确答案:C


The major disadvantage of a bar chart is:

A.Lack of time-phasing.

B.Cannot be related to calendar dates.

C.does not show activity interrelationships.

D.Cannot be related to manpower planning.

E.Cannot be related to cost estimates.

正确答案:C
C


你在管理开发一种有很大争议的转基因酶来生产一种无脂肪的鸭子。这种酶必须满足政府的卫生标准并能产生一种用户期待的鸭子。昨天,你开了一个团队会议,向队员们解释了项目的目标。团队中有6个人是反对转基因食品联合会的持卡会员,他们立即站起来引证哲学的和道德的基本原则来反对该项目,并离开了会议室。你追他们到大厅并劝他们留在项目工作,并说你将对该项目采用最好的质量管理计划。其中一个队员突然停下来并要求知道这样一个计划是做什么用的。你解释说任何质量管理计划的目标是——

A.保证将遵守所有用动物进行实验的条例

B.保证及时进行过程调整

C.全面提高项目执行的质量

D.确保按照质量管理计划进行

正确答案:C


幅度估计可以识别以下各项目,除了:

A、 出现成本超支的算术概率

B、 根据底线重要性对风险和机会进行排序

C、 达到一定置信度的可能性

D、 影响估计的具体风险事件

正确答案:D


During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

A.Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

B.Let the affected line groups decide among themselves who will perform. the work

C.Ask the executive sponsor to make the decision

D.Allow each line group to perform. part of the task

E.All of the above

正确答案:B

 


21年项目管理师经典例题8卷 第4卷


113 Screening of risk events for potential risk is known as _____ .

A. problem structuring.

B. risk identification

C. risk quantification

D. risk modeling

E. risk mitigation

正确答案:B


In acceptance sampling, if the sample size is kept the same but the acceptance number is increased, which of the following will be true:

A . buyer's risk will decrease

B . vendor's risk will decrease

C . producer's risk will decrease

D . consumer's risk will increase

E . C and D only

正确答案:E


15 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:

A. the message was understood

B the message was not understood

C. the subordinate discarded the information

D. the information was not appropriate

E. None of the above

正确答案:E


某天晚上下班的时候,由于司机休假,你们公司的(CEO)不得不自己开车。但是他怎么也找不到出楼的路,加上他本来已经比较疲惫了,所以他感到非常恼火。第二天就找人要改善本楼的出入系统,以方便大家进出。而你正是这个出入系统的项目经理,你决定用流程图来做什么事情?

A.帮助分析问题是如何出现的

B.表明任务之间的依赖关系

C.说明一个流程的结果

D.预测未来成果

正确答案:A


Which of the following areas are addressed in risk identification:

A environmental

B technical

C legal

D All of the above.

E A and B only

正确答案:D


40 The accounting head asks an assistant to cut the payroll checks today. The head later arrives to sign the checks, only to find that the assistant shredded (cut) the blank check forms. Which phrase best describes this lack of communication.

A. Bypass instruction

B. Faulty perception of reality

C. Bad attitude of listener

D. Lazy listening

E. Emotionalism

正确答案:A


124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?

A. $1,020

B. $1,010

C. $1,015

D. $20.00

E. None of the above

正确答案:E


21年项目管理师经典例题8卷 第5卷


● Proper implementation of project management will guarantee that:

A Budgets will be met.

B Schedules will be adhered to.

C Quality/performance will be met.

D The project will be a success.

E None of the above.

正确答案:E


● The project life-cycle can be described as:

A project concept, project planning, project execution, and project close-out.

B project planning, work authorization, and project reporting.

C project planning, project control, project definition, WBS development, and project termination.

D project concept, project execution, and project reporting.

E All of the above.

正确答案:A


下列哪一项是建立在一个较有能力的个人魄力之上( )

A.专家权力

B.奖励权力

C.参照权力

D.A及B

E.A及C

正确答案:C


项目执行期间,进度绩效和成本绩效均令人满意,这时重新委任了一个项目经理,他正出席见面会,什么是是最重要的?

A、 设定目标

B、 向项目干系人人介绍小组成员

C、 检查沟通

D、 项目章程

正确答案:C


如果项目经理不关心个人目标而是关注关系问题,那么他采用的是哪类冲突解决方法?

A、 得-失

B、 屈服-失

C、 失-离开

D、 妥协

正确答案:B


124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?

A. $1,020

B. $1,010

C. $1,015

D. $20.00

E. None of the above

正确答案:E


在项目执行中进度和成本执行绩效令人满意这时指派了一名新的项目经理他正在参加见面介绍会最重要的是什么( )

A.设定目标

B.向项目干系人介绍项目队伍成员

C.检查沟通

D.项目章程

正确答案:C


21年项目管理师经典例题8卷 第6卷


45 All of the following statements define the role of a meeting chairperson except:

A. Initiates and concludes discussion

B. Controls irrelevant discussion

C. Resolves strong disagreements

D. Produces meeting agenda

E. Consolidates agreements

正确答案:D


34 Things that distort, distract, or muddle the communication process are called:

A. noise

B. selective filtering

C. selective perception

D. medium problems

E. All of the above

正确答案:A


一个科学家正通知技术人员一个已开始研发的产品以及实验室技术人员将被希望进行的工作那么影响技术人员过滤这些信息的能力的障碍如下除了( )

A.语言及语义

B.文化及宗教

C.文化水平

D.信誉权威组织状态

E.实验室及科学家办公室的位置

正确答案:E


The LEAST effective form. of communication for complex situations is:

A verbal - face to face

B written

C formal

D informal

E A and C

正确答案:E


新的计算机系统某个非关键路线活动将延迟通常可靠的供应商已经表示一个可接受的修改交货时间由于计算机延误项目经理应 ( )

A.实行合同罚款

B.评估延误和确定备选方案

C.查找替代供应商

D.延迟项目知道计算机供应商赶上进度

正确答案:B


哪个过程是从风险拥有者处接受输入?

A、 风险管理规划

B、 风险识别

C、 风险定性分析

D、 风险应对规划

正确答案:D


各种项目的档案资料可以用于( )

A.将目前的业绩和预期获得的教训与之相比较

B.准备干系人管理计划

C.筛选项目团队成员

D.作为项目开始的输入项

正确答案:D


21年项目管理师经典例题8卷 第7卷


116 Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:

A. 1.4

B. 0.8

C. 0.2

D. 0.12

E. None of the above

正确答案:D


10 On a precedence diagram, the arrow between two boxes is called:

A. An activity.

B. A constraint.

C. An event.

D. The critical path.

E. None of above

正确答案:B


194 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

A. P

B. Q

C. R

D. S

E. T

正确答案:A


计划评审技术(PERT)是项目进度安排的一种方法。在风险的上下关联上,PERT 比关键路径方法好,因为它处理_______同_______的关系。

a. 逻辑,成本估计

b. 逻辑,进度估计

c. 确定性,成本估计

d. 不确定性,进度估计

e. 确定性,进度估计

正确答案:D
d [PERT 最初用于处理一个特殊的时间进度框架内完成全部任务(确定的)的可能性。]


自从3000年前第一次保龄球运动引入到你的国家,你的国家一直将保龄球运动视为一种高尚的运动。你作为一个项目经理要为政府建造一个保龄球运动的纪念碑:一个大理石一钛结构的保龄球饰针。这个纪念碑预期能够持续几个世纪。在这种情况下,认为项目是暂时性的这种说法( )

A.不适合,因为这个项目需要的结果是持续的

B.不适合要建造的产品

C.认为项目团队将比本项目要长寿

D.不适合,因为这个项目不是在短期内可以完成的

正确答案:B


你负责管理一组人员,你们要从三个项目中选择出一个来。这个项目是开发一种针对痱子热毒的解毒剂。在会议上,许多小组成员已经决定使用何种项目技术。有些倾向于使用内部回报率(IRR),有些则主张使用收益成本率(BCR)。在决定使用的方法时,你的第一步是

A、 比较选择技术,辨别各自的优缺点

B、 如果适用于项目,使用公司应用最多的技术

C、 使用大多数小组成员都了解的方法

D、 明确本公司管理的哲学和意愿

正确答案:D


在执行项目期间,发生一个在风险管理计划中没有涵盖的重大问题,这时你将: ( )

A.建立一个权便措施

B.召开会义采用头脑风暴法

C.向高层管理汇报

D.从管理储备抽出资金作为处理成本

正确答案:A


21年项目管理师经典例题8卷 第8卷


42 In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

A. unit price

B. cost plus incentive fee

C. cost plus fixed fee

D. firm fixed price

E.B and D only

正确答案:D


下列哪一项会影响网络计划的工期( )

A.资源库的技能水平

B.年份日期

C.约束条件

D.以上都正确

E.A及B正确

正确答案:D


“质量成本”是一个项目管理概念,它包括下列哪项成本?

A、 超过要求

B、 要求变更

C、 保证符合要求

D、 质量控制要求

正确答案:C


在一个环境改造项目中,以下哪项是一个增值变更的范例?

A、 由于政府规定经过修订,需要重新提交设计

B、 利用按照原来定的范围不可获取的可以降低成本的技术

C、 合用材料清单定义项目的整个范围,包括所有的组件和子组件

D、 修正系统设计中遗漏的但应该有的特征

正确答案:B


在一个环境改造项目中,以下哪项是一个增值变更的范例?( )

A.由于政府规定经过修订,需要重新提交设计

B.利用按照原来定的范围不可获取的可以降低成本的技术

C.合用材料清单定义项目的整个范围,包括所有的组件和子组件

D.修正系统设计中遗漏的但应该有的特征

正确答案:B


3 In order to achieve long-term quality improvements, management must do the following:

A. Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

C. Implement of a formal quality control program with worker and management involvement.

D. Establish financial incentive packages for worker.

E. A and D

正确答案:C


挣值这一概念的主要缺陷在于:

A、 和当前WBS联系起来时不能确定客户的项目范围

B、 一旦计算出已完成的工作预算成本,要想对项目成本采取纠错行动已为时过晚

C、 提供已完工百分比准确估算的能力

D、 没有缺陷

正确答案:C