一个期望营造易于接受的沟通气氛的项目经理应该

a. 确保所有交流清晰易懂

b. 以他或她自己喜欢的方式与别人交谈或纸上交流

c. 让项目组准备一个项目沟通计划

d. 确保项目组成员获得其任务所需的信息

e. 确保项目组成员获得便利的工具。

正确答案:B
54.  b.  Speak or write as he or she would like to be spoken or written to   
By setting an example that others can follow, the project manager can encourage a free and
open exchange of ideas in a respectful and nonthreatening environment.


在项目组的工作中,项目经理发现了快速跟进的方法是在任务B开始5 天后任务D 开始,随后同时进行 10 天。

它对项目有什么影响?

a. 项目将早10天完成

b. 关键路径将改变

c. 项目将早5天完成

d. 任务G的工期将缩短5 天

e. B 和 c

正确答案:E
e. [ 因为任务 B 和 D 的开展将是平行的 10 天, 关键路径转移到任务 C、E、F ,和最后的H。这也使整个项目的工期从 33天缩短到了28天,减少5天。]


172 Communication plays a major role in:

A. Planning

B. Organizing

C. Controlling

D. Directing

E. All of the above

正确答案:E


149 The Communications Management Plan should contain the following:

A. Communications policy

B. Communications media

C. Reporting channels

D. Selection of appropriate media to meet specific needs

E. All of the above

正确答案:E


In which of the following cost estimating techniques are statistics models used:

A . nonparametric cost estimating

B . parametric cost estimating

C . life cycle cost estimating

D . bottom-up estimating

E . All of the above.

正确答案:B


21年项目管理师历年真题和解答7篇 第2篇


在定义项目范围和活动的过程中要使用到分解技术,但是该技术在定义范围和定义活动过程中起到的是不同的作用。从两者对比的角度来看,下列哪项陈述最好地说明了该技术在定义活动的过程中的作用?

A、 用工作分解结构WBS中的工作包来描述最终的产出

B、 把最终的产出描述为可交付的或切实的条目

C、 把最终的产出描述为行为或行动步骤

D、 分解技术在范围定义和行为定义中的作用是一样的

正确答案:C


范围核实 ( )

A.改进成本及计划的准确性对于使用革新技术及工艺的项目尤为重要

B.是项目移交给前客户的最后一项活动

C.将项目实施励则是产出的产品及服务特性制成文档

D.与质量控制有区别范围核实与工作结果的验收有关而不是更正

E.检查WBS是否是根据组织的项目管理理论来建立的

正确答案:D


质量保证的主要功能是:

A.为质量提供一定的保证

B.为延迟付款提供依据

C.为接收产品之后提供额外的时间纠正缺陷,而不产生额外的成本

D.保证购买的货物符合使用目的

正确答案:A


合同激励的最终目标是:

A、 承包商节约成本

B、 业主节约成本

C、 增加承包商利润

D、 协调合同双方目标

正确答案:D


Which of the following is equivalent to a lump sum contract:

A fixed price contract

B price fixing contract

C purchase order

D All of the above.

E B and C only

正确答案:A


21年项目管理师历年真题和解答7篇 第3篇


34 There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.

A. Management reserve, unplanned allowance fund.

B. Management reserve, contingency.

C. Contingency fund, management reserve.

D. Unplanned allowance fund, budgetary reserve.

E. Unplanned reserve, planned reserve

正确答案:C


All of the following are categories of a milestone in a schedule except:

A.End date.

B.Contract dates.

C.Key events scheduled.

D.Imposed dates.

E.Task duration.

正确答案:E
E


Job continuity would be an example of _____ in Maslow's hierarchy of needs.

A Self-actualization

B Esteem

C Physiological

D Belonging

E Safety

正确答案:E


125 Clearly defined group goals are important because they _____.

A. motivate team behavior.

B. cause inner tension within team members until they are met

C. encourage member interaction

D. All of the above.

E. A and C

正确答案:D


项目正在紧张的进展之中,团队成员感到压力在逐渐增大,为了减少大家的压力,你决定要在每次的项目状态会议上都要进行能补充能量的瑜珈术部分。根据公司项目管理的统一方法,你在寻找这种服务的供应商之前应该准备好下列哪项文件?

A.工作说明

B.采购管理计划

C.评估方法

D.合同条款和条件

正确答案:B


21年项目管理师历年真题和解答7篇 第4篇


122 The profitability and technical data studies are provided in report format to owners and funders for acceptance. This type of report, used to solicit funding, is referred to as a(n) _____.

A. Project feasibility study.

B. Economic evaluation analysis.

C. Risk management manual.

D. Prospectus.

E. None of the above

正确答案:D


在执行管道项目的过程中管道分承包商提出对某种材料升级而不改变项目进度计划或成本在此项改变得到批准后该更改最好在何处记录在案 ( )

A.项目批准书

B.工作描述

C.工作分解结构

D.质量保障计划

正确答案:D


9 The best way to insure quality conformance is to _____.

A. distribute the responsibility to subordinates.

B maintain total control.

C. train each worker to implement the work.

D. inspect quality into the project.

E. None of the above

正确答案:C


有效的项目整合通常需要强调( )

A.项目团队成员个人能力

B.及时更新项目计划

C.对主要交接点进行有效沟通

D.高层管理控制

正确答案:C


76 During which phase of the project life cycle is the amount at stake lowest?

A. concept

B. development

C. execution

D. conclusion

E. C and D

正确答案:A


21年项目管理师历年真题和解答7篇 第5篇


111 The WBS is:

A. An organization oriented family tree of the project.

B. A task oriented family tree of the project.

C. A cost centered structure of the project.

D. Only required on large complex projects where separately identifiable work packages are difficult to construct.

E. None of the above

正确答案:B


某项目经理想针对计划项目的实际结果编写报告,他会采用:

A、 趋势报告

B、 预测报告

C、 状态报告

D、 变量报告

正确答案:D


Methods and techniques used to examine cost and technical data are called feasibility studies. The economic aspects of a feasibility study include interest rates, present worth factors, operating costs, depreciation and _____.

A . Capitalization costs.

B . Technical skill requirements.

C . Technology forecasting.

D . Strategic marketing intelligence.

E . All of the above.

正确答案:A


你同项目小组讨论控制时间表的最佳途径,你希望能够控制那些改变项目进度的因素。同时你还想知道进度在什么时候发生变化,这样你可以采取相应的控制措施。你同小组成员讨论如何为衡量和报告项目进度作准备,为此你同意利用以下:

A、 进度表管理计划

B、 网络图表

C、 项目进度表

D、 技术基线

正确答案:C


107 In project-driven companies, costs are usually billed againest the project based upon:

A. The burdened labor rate of the actual employees who performed the work.

B. The burdened labor rate of the line organization average salary.

C. The burdened labor rate of the company average salary.

D. The burdened labor rate of the average salary of the project team members.

E. None of the above

正确答案:A


21年项目管理师历年真题和解答7篇 第6篇


你在管理一个有5个分包商的合同。你必须管理合同绩效、付款及管理与供应方的关系。一个分包商发出了变更其工作范围的请求。你检查了这一请求后决定修改合同。所有这些活动都是以下 的一部分?( )

A.合同管理

B.合同执行

C.合同格式

D.合同方案

正确答案:A


目标管理MBO假定一个团队( )

A.对一个非机构性环境来说是可接受的

B.不要求紧密的审查

C.掌握一个自我实施理论

D.以上都是

正确答案:C


● Project management/project planning is most closely aligned with:

A Long range/strategic planning (5 years or more).

B Intermediate range planning (1 to 5 years)

C Short range/tactical planning (1 year or less).

D All of the above.

E B and C.

正确答案:E


82 A program is characterized as:

A. a grouping or related tasks lasting one year or less.

B. a unique undertaking having a definite time period.

C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.

D. a project with a cost over $1 million.

E. None of the above

正确答案:C


18 Including the customer in the process of project planning is:

A. Slow and counterproductive.

B. Essential in the definition and documentation of project goals.

C. Necessary, but of limited value.

D. Unnecessary because project goals are defined in the proposal stage.

E. None of the above

正确答案:B


21年项目管理师历年真题和解答7篇 第7篇


158 Formal written correspondence is mandated in which of the following situations:

A. Product undergoes casual in-house testing

B. Client requests additional work not covered under contract

C. Project manager calls a meeting

D. B and C only

E. None of the above

正确答案:B


在项目计划编制的早期阶段,项目经理的领导方式是:

A、 教练

B、 支持

C、 代表

D、 指挥

正确答案:D


ISO 9000标准:

A、 说明如何生产品

B、 规定实施质量系统的细节

C、 为质量系统提供框架

D、 提供最大过程要求保证为客户提供优质产品

正确答案:C


亚伯拉罕·马斯洛提出了一个五个级别的需要层次理论,解释了一个人的整个生命发展周期中不同类型的需要。责任、成就感和能胜任的感觉属于下列哪个级别的需要?

A、 自我实现

B、 社会化

C、 尊重

D、 生理上

正确答案:C


质量管理计划描述了下面所有的条目,除了

A、质量政策实施方法

B、项目质量体系

C、实施项目质量管理所需要的组织结构,责任,程序,进程,以及资源

D、用来在成本、进度和质量中进行平衡分析的步骤

正确答案:D