2021项目管理师考试真题及答案5辑

发布时间:2021-10-14
2021项目管理师考试真题及答案5辑

2021项目管理师考试真题及答案5辑 第1辑


在什么情况下最适合使用Delphi技术?

A、 模似型已完成

B、 拥有丰富的历史资料

C、 规则是启发式的

D、 需要集体知识

正确答案:D


● A work breakdown structure is most useful for:

A identifying individual tasks for a project

B scheduling the start of tasks

C developing a cost estimate

D determining potential delays

E A and C

正确答案:E


执行任务的个体员工

A、 对结果符合要求或规范承担最终责任

B、 是重大项目组设计的一部分,只有项目经理了解项目组的性质

C、 不能对整体项目起到明显作用,

D、 不应该关心任务质量,因为对于整体项目范围而言,他/她的贡献是微不足道的

正确答案:A


有效的沟通对于项目的成功至关重要。范围变更、限制条件、假设、整合与界面要求,重叠的只能和职责以及其它许多因素都对沟通提出了挑战。沟通上的障碍很可能导致:( )

A.生产力下降

B.敌意增强

C.士气低落

D.冲突增加

正确答案:D


Which of the following is associated with a buyer's request for material to meet a particular need:

A material warranty

B material guarantees

C implied warranty of salability

D implied warranty of fitness for a particular purpose

E A and C only

正确答案:D


68 The Cost Performance Index (CPI) measures:

A. cost of work performed vs planned costs.

B. work performed vs cost of work performed.

C. work performed vs planned work.

D. direct costs vs indirect costs.

E. floating costs vs. sunk costs.

正确答案:B


25 In which of the following scope management processes is the scope management plan prepared? A. Initiation

B. Scope planning

C. Scope Definition

D. Scope change control

E. Scope verification

正确答案:B


2021项目管理师考试真题及答案5辑 第2辑


79 Time management is the allocation of time in a project's life cycle through the process of:

A. Planning

B. Estimating.

C. Scheduling.

D. Controlling

E. All of the above.

正确答案:E


书面变更命令应该在什么时候需要( )

A.所有的项目,无论大小

B.只有大的项目才需要

C.那些有一个合适的、正式的、范围变更管理系统的项目

D.那些变更控制系统的成本可以调节的项目

正确答案:A


当记录到实际测量到的质量特征时,如用千分之一英寸表达尺寸,质量是用什么来表示的?

A、 特性

B、 变量

C、 属性

D、 性质

正确答案:B


185项目经理可以通过以下措施提高项目的沟通效率以及项目小组的建设,除了:

A.设立一个“作战室”

B.作为良好沟通的阻碍者发挥作用

C.作为一个项目促进者发挥作用

D.举行高效率的会议

正确答案:B


当你在检查项目的成本绩效数据的时候,对于基准线偏离的不同程度要求作出不同的反应。例如,10%的偏离可能不要求立即行动,而100%的偏离将要求调查研究。一个描述你计划怎样管理成本偏差的计划是( )

A.成本管理计划

B.变更管理计划

C.业绩衡量计划

D.计划偏离管理计划

正确答案:A


Risk management requires an understanding that _____ .

A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

B risk identification must be directly aligned with the Work Breakdown Structure.

C it is merely advanced preparation for possible adverse future events.

D it does not imply complete control of events

E All of the above.

正确答案:E


The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A . budget, schedule

B . quality requirements, schedule

C . size, type of industry

D . nature, size

E . project manager, sponsor

正确答案:D

 


2021项目管理师考试真题及答案5辑 第3辑


以下各项除了( )均为团队建设技术?

A.工作场地外搞活动改善小组成员间人际关系

B.奖励和认可制度

C.开工准备会议

D.项目经理平息小组冲突

正确答案:D


137 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:

A. $19K

B. $21K

C. $26K

D. $29K

E. indeterminate

正确答案:C


如果完工比例是60%,完工预算是20000美元,实际成本(实际成本或已完成工作实际成本)15000美元,则成本偏差(CV)和进度计划(SV)偏差是多少?

A、 信息不充分,无法计划CV和SV

B、 CV=SV=-3000美元

C、 CV=-3000美元、SV=+3000美元

D、 CV=-3000美元、信息不充分无法计划SV

正确答案:D


项目团队应该具备有关统计过程控制的专业知识来帮助从事质量控制活动。在所有相关的话题中,以下哪一点最重要因而是需要团队理解的?( )

A.抽样和概率

B.属性抽样和变量抽样

C.偏差和控制界限

D.特别是原因和随机原因

正确答案:A


以下各项关于规避风险的陈述除了---------都是正确的

A、 关心消除引起风险的元素

B、 包括决定不对风险过高的项目进行投标

C、 风险倘若发生,就接受后果

D、 当客户对利于降低风险时,将风险遗留给客户

正确答案:C


194 Management decision-making includes:

A. Analysis of alternatives.

B. Revisions/replanning.

C. Resource allocation.

D. Modification or updating of goals and objectives.

E. All of the above.

正确答案:E


25 In which of the following scope management processes is the scope management plan prepared? A. Initiation

B. Scope planning

C. Scope Definition

D. Scope change control

E. Scope verification

正确答案:B


2021项目管理师考试真题及答案5辑 第4辑


66 Which of the following activities can be considered as part of risk mitigation

A. risk identification

B. purchasing insurance

C. assessment of outcomes

D. assessment of probabilities

E. C and D only

正确答案:B


过滤这个概念在什么时候出现?

A、 一个技术结合项目沟通计划使用时

B、 监督人执行沟通信息审核和文档记载时

C、 在上下级之间的沟通中大部分信息丢失

D、 A和B

正确答案:C


当项目团队成员并非集中在同一地点办公时这些成员之间的相互影响及了解都有限在这种情况下的项目经理应该( )

A.设法使团队成员相互了解相互促进

B.定期如开面对面的团队会议

C.将小组成员按项目各部分工作分成小姐共同工作

D.收集并奖励团队成员的意见

E.以上都是

正确答案:E


An acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chart

A . When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process

B . When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.

C . When a process is subject to constant but stable tool wear.

D . A and B.

E . A and C

正确答案:E


你的项目发起人要求你为项目进度风险进行一个蒙特卡罗分析。这个任务需要用到下列哪一部分内容?( )

A.编制项目计划的方法

B.项目执行的方法

C.项目管理信息系统

D.项目经验教训数据系统

正确答案:A


你所在的公司原来主要生产是一家处于领先地位的食品供应商。为了增加公司收入,管理者有意开拓新的市场和产品。你现在领导着一个负责开发产品的团队。由于你的背景和对信息技术的兴趣,你建议公司开发无线通信产品。但当你将建议提交审议的时候,管理层认为这项产品和公司的核心竞争力不符合。你需要返回规划委员会推荐其他产品,并把管理层的指导方针作为( )

A.一条假设

B.一项约束

C.一个规范

D.一项技术要求

正确答案:A


质量计划编制的时候,应该由谁通知项目干系人质量政策?

A、 组织领导

B、 项目经理

C、 项目团队

D、 职能经理

正确答案:C


2021项目管理师考试真题及答案5辑 第5辑


19 "Paraphrasing" is most closely associated with which part of the communication process? A. encoding

B decoding

C. barriers

D. feedback

E. None of the above

正确答案:D


131 The most effective team motivator is:

A. the visibility of the team's contribution

B. the satisfaction of meeting a challenge

C. understanding the importance of the project

D. the individual's professional challenge

E. All of the above

正确答案:A


The reason that cost management is so difficult in project management is that:

A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.

B . There are no tools for identifying project tasks.

C . Project managers do not care about tracking costs, as only schedules are important to all project managers.

D . A and B only

E . B and C only

正确答案:A


你正管理一个重要的国际项目,你的客户最近得了MalColm BalDrige质量奖,并在其所有的工作中强调质量。你的合同要求你既要准备一份项目计划又要准备一份质量管理计划。你的核心团队正在准备一份项目质量管理计划。你发展这一计划的第一步是——( )

A.决定在质量管理过程中用什么单位制

B.确立项的质量标准

C.为项目制定质量政策

D.为项目确立明确的质量管理任务和职责

正确答案:C


64 The financial closeout of a project dictates that:

A. All project funds have been spent.

B. No charge numbers have been overrun.

C. No follow-on work from this client is possible.

D. No further charges can be made against the project.

E. All of the above

正确答案:D


61 In small companies, project managers and line managers are:

A. Never the same person

B. Always the same person

C. Sometimes the same person

D. Always in disagreement with each other

E. Forced to act as their own sponsors

正确答案:C


项目执行期间重新委任了一名项目经理,项目已经按照计划执行,但是项目经理发现客户对报告方法相当不满,项目经理应该首先做什么?( )

A.检查沟通系统

B.询问客户的不满和要求,找出解决方案

C.向客户建议修改报告

D.让项目团队制定替代方案

正确答案:B